What Does It Cost to Confirm Your Lot Can Actually Take an ADU Before You Commit?
Watch: ADUs, Nursing Homes & Inheritance: What Families Get Wrong, Atty. Brian Barreira
You'd like to build an ADU in the backyard for your mother, father, or grown child but there's a question that stops you. What if you aren't allowed to put one on the lot you have? You don't want to pay for the surveys and soil tests and then find out you can't move ahead. And you don't want to sign a construction contract when you're only guessing either. These concerns are reasonable, and both of them come from the same issue: you don't know what it will cost to get an answer.
My name is Buz Artiano, and I am the founder of BuildX. We've built dozens of ADU projects across Massachusetts, mostly around the South Shore and Plymouth County areas. We are the only team you need: we do the design, permitting, and construction. So we see every phase of a project from the first site visit up until you move in. We evaluate septic constraints, zoning issues, utility connections and the requirement to get a permit from the city. All of our projects have started with a question just like you're asking now.
We make decisions based on how likely something is to happen. If a property can have an ADU on it will depend on a short list of things: the septic system, the utilities, size of the lot, and if you are on the town's sewer system, if they'll allow you to connect. On a lot that already has septic, there are three different types of paid work that will give you the answers: a survey, a perc test (a percolation test of the soil), and Title V septic work. But before you do any of that there's a step that doesn't cost anything. Every level has a price and each gives you additional confidence. You need to know what these are before you spend any money. If you should spend any money at all also depends on your family situation which is more important than any of the factors.
Quick Answer: Confirming your lot has two steps. For no charge at all we hold a Zoom meeting where we lay your property out in our software. This will tell you with about 85% accuracy if an ADU is likely to work for you. In 2025, we estimated it would cost about $5,000 to $10,000 to have a survey, a perc test, and a Title V septic evaluation done and those will get you to about 99% certainty that your property works for an ADU. If your ADU will use town sewer, first check with the town that it will allow another unit. We'll tell you what you need to check for your lot and what each test will cost before you okay them. Both percentages are our rule of thumb, not a proven statistic.
In This Article
- What Will I Pay to Know My Lot Can Take an ADU?
- What Do I Learn Before I Spend Anything?
- What Does the $5,000 to $10,000 Estimate Pay For on a Septic Lot?
- What Should I Ask a Builder Before I Pay for Testing?
- Should I Stop at the Free Assessment?
- Find Out Where Your Lot Stands Before You Spend a Dollar
What Will I Pay to Know My Lot Can Take an ADU?
You don't have to pay anything to get to about 85 percent. If your lot needs a survey, a perc test, and Title V septic work, we figured $5,000 to $10,000 in 2025 to get to about 99 percent certainty that we can build your ADU. That's the rule we use at BuildX. Before you okay any testing to be done, be sure you ask for a written quote that shows the total you'd pay.
Look at those numbers for what they are. The 85 and the 99 are our rule of thumb after building dozens of ADUs, not success rates that can be measured. This cost range is from 2025, and survey and testing prices change.
Every builder has to deal with the same questions about any property before construction starts, because rules for the septic and the property lines will be the same no matter which builder you choose. But the timing and the price of that answer can change from builder to builder. Just think of our numbers as one example and then compare them with what other builders tell you.
What Do I Learn Before I Spend Anything?
The first thing we do with a possible client is hold a Zoom meeting. We have software that lets us lay everything out with you on screen, and we answer one question: is it likely this will work? That happens before you have to spend any money.
This step is the first thing we do because of the concerns that people come to us with. If you don't want to spend a lot of money only to find out that your lot won't work for an ADU, the steps need to be in order for your protection. You'll get an answer that costs you nothing if it's likely you can't move forward and that answer won't cost you anything. We can talk about the paid test part when a lot has an 85 percent chance of moving forward.
The free step is done on a screen. It shows how a lot is laid out. It doesn't dig any holes or do any measuring, so it doesn't show how your soil drains or exactly where your property lines are. The paid work will answer those two questions.
What Does the $5,000 to $10,000 Estimate Pay For on a Septic Lot?
If your septic system passes the free test, then we think it's time to start spending some money. The $5,000 to $10,000 we estimated in 2025 gives you three things:
- A survey that shows where your property lines are and how much room the lot has for a new structure.
- A perc test measures how fast water drains through your soil.
- Title V work checks the septic part of the project with the Massachusetts septic code.
Title V states that you have to have your site evaluated before a septic system can be installed, to make sure the soil can deal with the waste load. Only a licensed professional can do the soil evaluation. The state tells you who's qualified to do that work at mass.gov.
The work is done in order. We'll tell you about each problem and what it's going to cost to figure it out, and eliminate those one at a time.
Why Is Septic the Biggest Unknown on My Lot?
We call utilities and septic "the wild card" on any ADU project. And for the septic the reason is the Department of Environmental Protection, because the septic has to follow their rules and DEP is very strict about what you can do.
You also can't put an ADU on top of a septic system. The survey and the perc test will be the first money we'll ask you to spend on a lot that has septic. Until the soil's tested and the lines are measured, there's a question about where the septic system can go and the location of it will limit where the actual ADU can be built.
The size of your lot will decide how hard that is. If you have plenty of land that leaves room for the septic in one place and your ADU in another. But tight lots are tough. If your lot is tight, the paid testing is when you'll find out whether both of those will fit.
If your house is on the town sewer system then you need to deal with this question: is the town allowing additional connections? A lot of towns have had moratoriums, which means a complete stop or freeze, on new connections because the infrastructure wasn't able to handle any more. That can get tricky, and the answer will come from the town.
What Should I Ask a Builder Before I Pay for Testing?
The same four questions apply to us and to every other builder that you talk to. A builder who's done this kind of work should have an answer for each one.
- What do you check on my lot before I spend any money?
- What does each piece of paid testing cost on my lot?
- How much confidence will you have after each step?
- What happens on my lot if the septic or the town sewer connection is the problem?
You should require every builder, including us, to give you the same amount of detail on those questions. An answer that doesn't give you a cost and a level of confidence is a risk to you.
Should I Stop at the Free Assessment?
Since we build ADUs for a living, you'd think we'd tell every family to spend the money. We don't. For some families, stopping with the free assessment is the right decision.
You should stop if the first free step gives you a low probability that the project can move forward. This answer doesn't cost you a thing.
You should stop, or at least pause, if your family hasn't agreed to a plan. Our rule is that an ADU project is 70 percent family dynamics and 30 percent what we're going to build. That makes family the first thing that can change the project, even before septic. A perc test can't decide who's going to live in the ADU or who's paying for it, so don't put out any money until your family has settled those issues.
Be clear about what the paid work is. It's testing. A perc test reports what your soil does, and the result might be one that you didn't want to hear. About 99 percent is how certain we are when the work is finished. It isn't a promise that we make before the results come back and it's not 100 percent.
Find Out Where Your Lot Stands Before You Spend a Dollar
The decision you have to make is how certain you want to be before you make a commitment, and you should make it in order. Get your free answer first.
If your lot already has a septic system, just pay for the testing only if the free answer is positive and your family is ready. On town sewer, the town's answer on capacity has to come first.
We will lay out your property on a Zoom call at no cost and tell you whether an ADU has a high probability of working before you spend a dollar on a survey or a perc test.