Will Upgrading the Glass in My ADU Windows Delay the Build?
Watch: Why Your Home Feels Dark, Even With Big Windows | Joe Menchefski Explains
You've got a floor plan that you love and while you were talking about windows and someone mentioned upgraded glass. That is glass that spreads out daylight, insulates or will give your bathroom privacy without using a blind. Your worry is that if you have to place a special order that it might mean your framed ADU will be open while the crew wait, and that means that the move in date for your parents, your rental income or maybe even your own move in date has to wait too. Your first reaction is just to use whatever glass the builder has in stock and stop asking questions.
My name is Buz Artiano, founder of BuildX. We've built dozens of ADUs in Massachusetts, and most of those are on the South Shore and in Plymouth County. They all have to pass a septic evaluation, follow the lot coverage limits, and get by-right permits before any windows get ordered. We do all design, permitting, and construction from one office so your window order and the construction schedule are all on the same calendar. If you have questions about your glass order, we can see exactly what's going on from the calendar.
We asked Joe Menchefski of Advanced Glazings, a manufacturer of translucent, light-diffusing glass this same question when he was in the Just Build Baby studio. His answer is useful for anyone who's thinking about upgrading their glass. We give you a predictable cost for it and when you have to pay depends on when you decide what you want.
Quick Answer: To upgrade your glass can take extra time if it's a special order that is sent to the window manufacturer first, and you can plan for that extra time. Joe Menchefski of Advanced Glazings told us that his company's glass adds two to four weeks to a window order, because their glass goes to the window manufacturer first, such as Andersen or Pella, and then they build the finished window around the glass. Other suppliers have their own timelines. We can deal with the extra time if you choose the glass during design before the window package has been ordered. But if you decide after the order's been put in, the delay happens in the middle of construction.
In This Article
- How Much Time Does a Glass Upgrade Add to My ADU Schedule?
- Why Does This Glass Upgrade Add Time to My Window Order?
- Why Can't I Order Upgraded Glass Straight From the Window Catalog?
- When Do I Have to Decide on the Glass?
- What Should I Ask Before I Commit to a Glass Upgrade?
- Is Specialty Glass the Right Choice for Every ADU?
- Ready to Settle Your Window Glass During Design?
How Much Time Does a Glass Upgrade Add to My ADU Schedule?
When we asked Joe how much lead time this upgraded glass needs, he said about two to four weeks. He was just as honest about what that means, it doesn't take forever, but it's something you need to plan for. Lead time is the time between when you place an order and when the product is there and ready to install. Every window package has a lead time, and if you order special glass it can make it longer.
That amount of time is just Joe's estimate for his own company's glass when we were talking. It isn't the same for other suppliers or other upgrades, and it can change, so make sure to ask about the current lead time and get it in writing with your quote. He also didn't say if that time starts when the order is put in, when you make a deposit, or when the drawings are approved, so finding out the starting point should be on your list of questions.
So the answer is this: an upgrade that goes through this kind of process will lengthen your window order. It might delay your building but that depends on when that order is placed in relation to everything else that's on the schedule. And that timing is something you can control.
Why Does This Glass Upgrade Add Time to My Window Order?
The supply chain is the reason for this, and hardly anyone talks to the homeowners about it. Advanced Glazings doesn't sell you a window. We asked if they sell the whole window or just the glass and Joe's answer was only the glass. Their product, Solera, is called an IGU, which stands for insulated glass unit. That's two panes of glass that are separated by a spacer and sealed together in one piece. That part has to go inside a window frame that's built by another company.
Here's the order Joe gave us about when we asked him how we'd get his glass into an Andersen window frame for our builds:
- The homeowner or builder gets a hold of the glass company and gives them the brand of window.
- The glass company calls the window manufacturer and quotes a price.
- The window manufacturer then gives you the price of the finished window.quotes the finished window.
- The glass company ships its window frames to the window manufacturer.
- The window manufacturer builds the window around that glass and ships it to the building site.
Joe said his team has Andersen on speed dial, so that shows you that they do this all the time. which tells you the handoff is routine. It's also the reason for the extra time: the window manufacturer can't finish the window until they get the glass from Advanced Glazings.
There has to be a one inch gap in the sash, the frame inside the window that holds the glass. Joe said the company's windows for homes are almost always one inch thick, and he's worked with Pella. Having a gap that matches doesn't necessarily mean they'll fit. The window manufacturer has to check that the series and sizes on your plan will work for that unit, and that needs to be verified in the quote.
Why Can't I Order Upgraded Glass Straight From the Window Catalog?
Today, specialty glass is a special order instead of just choosing from a catalog and Joe was honest about why. Advanced Glazings has been in business for about 30 years, and most of the work they've done is for businesses. But over the last two or three years, architects who design houses have been finding the company. When we talked, they'd been giving a presentation for homes accredited by the American Institute of Architects (AIA) for less than six months.
Because of that, the company sells mostly through architects that are designing large high-end homes. They don't deal yet with contractors. Joe said that they can make it happen but today it's not as easy as it should be. Production is in Nova Scotia, with a second plant being built in Wilmington, North Carolina.
Joe said that ideally he'd like someone to be able to pick their glass from a window manufacturer's catalog, and that way the window comes on a truck ready to install. His company already works that way for metal buildings with a framing company in Missouri, where the buyers can order directly. But home windows aren't there yet. Until then, an ADU owner who wants this kind of glass has to place a special order using the process that's made for architects, and that increases the lead time.
When Do I Have to Decide on the Glass?
You should decide during design, while the window schedule is only on paper. That's the only control you have over how much time the glass upgrade will take.
From our side on the job site, here's how the windows work for the ADUs we build. The finished windows come on a truck, and then our crew puts them into the rough openings, which are framed holes in the wall made to fit each window. The insulated glass is all sealed at the factory. The easiest time to choose that glass is before the window's built. Changing it afterward will mean reglazing, getting a different sash, or maybe a different window, depending on the product. Each of these is a new order with more lead time.
That order is why glass should be talked about when you are discussing window size, frame material, and placement. The frame and the glass are two separate decisions that are made by two separate companies, and both of them have to be decided before you make your order for the windows. If you choose during design, then the lead time the supplier gives you is built into the order from the first day, so it can be planned for. But if you do it after the order, then the window package has to be redone. You will need a written change to the size, price or schedule of a signed contract. The new lead time will be added to wherever the build is now.
What Should I Ask Before I Commit to a Glass Upgrade?
Because the delay will come from the order chain, the questions that protect your schedule are questions about that chain. Before you decide on any specialty glass, get answers to these:
- Has the window manufacturer confirmed this glass will work with the exact series and sizes on my plan?
- Who gives the cost to whom, and will I get one complete price for each window?
- Does the lead time start at order, when I make a deposit, or when I approve the drawings?
- What is the total time from order to a finished window at my job site?
The cost needs to be discussed. Joe didn't give any price for his glass, and the process he talked about will have two quotes: one from the glass company to the window manufacturer and one from the window manufacturer to you. The cost of an upgrade is different from project by project, so get the finished window price in writing before the order is made.
Also ask what kind of effect the upgrade will have on insulation as well. Joe said his company's one inch residential unit is R5. R-value measures resistance to heat flow, and a higher number insulates better. That figure is the manufacturer's claim about its own product, so you need to verify it on the spec sheet for whichever unit window you are ordering.
Is Specialty Glass the Right Choice for Every ADU?
We don't have any business relationship with Advanced Glazings, and BuildX doesn't supply or resell its glass. We asked Joe these questions because our clients ask us about light, privacy, and glass, and we wanted this order process to be explained by the people who run it. With that said, the honest answer is that regular glass is the right answer for many ADUs.
If your window package has already been ordered, or you can't add lead time to your move-in date, then regular glass will keep your schedule the same. If your budget's been decided and an upgrade hasn't been discussed, regular glass takes away that option. And if your lot doesn't have glare, privacy issues, or an insulation problem that the upgraded windows would fix, there's no reason to add the special order windows. The upgrade is only worth it if it solves a real problem on your property and you decide soon enough to plan for it.
Ready to Settle Your Window Glass During Design?
If you decide to upgrade your windows, that's a time decision as much as a design decision. If you make it during design then it will be a planned-for part of your window order but if you wait, it reopens the package in the middle of the build. So if upgraded glass is something you're interested in, talk about it now, while it still fits the schedule.
We'll review your window package with you during design, show you which glass choices are in stock and which have to be special ordered, and put any additional lead time in your schedule before we order.